Sunlit pale stucco arch surrounding bronze-framed glass doors, with a limestone terrace and a single sea grape tree.

Naples Pier Rebuild: What to Expect Before July 2027

On October 7, 2026, Shoreline Foundation Inc. drove the last of the 193 reinforced-concrete pilings for the new Naples Pier. That came less than a month after crews finished the mid-Pavilion concrete pour on September 18, which put the project past the halfway mark for concrete. The contractor expects to finish all structural work by early 2027 and then install the decking. The City still has the reopening on schedule for July 2027.

The pier going up at the end of 12th Avenue South will look familiar from the beach, but nearly every change you'll notice when it opens comes from designing it to survive the next major storm. Until then, the pier's everyday uses are spread out, some along the shoreline and some under 10 miles of Gulf water.

A Landmark That Has Been Rebuilt Again and Again

The City dates the Naples Pier to 1888 and counts more than one million visitors a year who come to fish, meet up and watch wildlife. Hurricanes forced major rebuilds after storms in 1910, 1926, 1944 and 1960. A significant renovation followed in 2015. Hurricane Irma damaged the pier two years later, and Hurricane Ian hit it far harder in 2022.

Ian came ashore near Cayo Costa on September 28, 2022, about 104 miles from Naples, as a Category 4 storm. Even at that distance, around 140 feet of the pier, including the end shelter and more than 30 pilings, ended up on the Gulf floor. Waves gutted the concession area, the midpoint shelter and the storage buildings. City engineers decided the structure was compromised and that full replacement made more sense than repair.

So the question behind the new design was what a pier needs to stand up to a storm that wrecked it from more than 100 miles away. The City's answer shows up in the specifications.

What Changed Below the Deck

The design team, led by Turrell, Hall & Associates with MHK Architecture, cut the number of piles and spaced them farther apart to reduce erosion and impact on the shoreline. They also made each pile bigger.

Feature Previous pier New pier
Pile size 14 inches square 18 inches square, a 65 percent increase
Pile length Shorter than the new piles 70, 85 and 100 feet, all longer than the old pier's longest
Deck height Baseline Three feet higher above the water
Poured concrete Baseline Nearly three times as much
Mid-pier food service Concession building Portable food and beverage carts
Police presence No substation on the deck Small Naples Police/Beach Patrol substation

The longer, wider piles give the structure enough capacity for the City to raise the deck three feet. The extra concrete makes it more likely that the concrete portion of the pier would come through a severe hurricane. The full project calls for about 602 cubic yards of concrete.

The walking surface is designed for durability too. The decking is ipe, pronounced "ee-pay," a tropical hardwood the City describes as durable and resistant to rot. Two-thirds of it had arrived by July 24, 2026, and it goes down only after the concrete work is finished.

Why Carts Are Replacing the Concession Building

The bottom two rows of that table are the changes regular pier visitors will feel most. State and federal rules did not allow the old mid-pier concession area to be rebuilt. The City Council weighed several options and chose portable food and beverage carts at the mid-pavilion, an approach the City says serves visitors while respecting neighboring residents and businesses. Council also approved a small Naples Police/Beach Patrol substation on the pier.

The old concession area was one of the structures Ian's waves gutted. With no permanent building to replace it, the mid-pier stop will work differently, built around carts rather than a counter.

The structure also had to be paid for. The City puts the total at about $26 million including design and permitting, according to Naples Press, which listed the funding sources as $11,401,144 from FEMA within $12,667,938 in federal funds, $633,396 in state funds, a $5 million state appropriation, $2.2 million from the county Tourist Development Council, city beach funds and public donations, including from the Collier Community Foundation. Because FEMA, state and TDC money arrives as reimbursement, the City issued $11 million in bonds to cover costs in the meantime. Gulfshore Business reported the construction contract at $23.45 million, plus a $1.17 million contingency for unforeseen problems, and described the rebuild as a $26.3 million project. The small gap between the two totals comes down to scope and rounding.

When FEMA obligated its share on December 12, 2025, Mayor Teresa Heitmann told Gulfshore Business:

"This is truly a wonderful Christmas gift for our residents and for everyone who treasures the Naples Pier."

Where the Old Pier Went

The old pier is still in the Gulf. The City finished demolition on April 13, 2026. On April 24, crews placed 59 of its concrete pilings at Wasmer Reef, expanding an artificial reef first built in 2015. The Naples Daily News reported in an April 30 photo gallery that the reef sits 10 miles out in the Gulf off Gordon Pass.

Before the new pilings could go in, a month-long diving effort that began May 5 cleared debris from the site, including pilings from the 1990s that were still buried there. Material from more than one earlier version of the pier came out of that seabed before the new one was built.

How the Beach at 12th Avenue South Works This Winter

Until July, the pier itself, its stairs, restrooms and showers, and 12th Avenue South west of Gulf Shore Boulevard South are all closed. Only the western third of the pier parking lot at 12th Avenue South and Gulf Shore Boulevard South is open to the public. The eastern two-thirds is in use for construction.

The City has set up pedestrian bypasses at the Broad Avenue South and 13th Avenue South beach ends, one on each side of the site. Both will stay open for the whole project, and both have restrooms. If you want facilities beyond those two beach ends, Lowdermilk Park is open from 5 a.m. to 11 p.m. and has restrooms, showers, benches and beach-access mats.

For anglers, the closure affects licensing as well as location. Florida exempts anglers who fish from a licensed pier from the shoreline license requirement. Fishing from the beach falls under the shoreline rules instead. Florida residents who fish only from land, or from a structure attached to land, can get the free resident saltwater shoreline license. Anyone who already holds a regular saltwater license, which costs $17 for residents and also covers fishing from a boat, doesn't need the shoreline version. Residents 65 and older and children under 16 are among the exempt groups. Nonresidents can't get the shoreline license. They need a nonresident saltwater license, priced by the Florida Fish and Wildlife Conservation Commission at $17 for three days, $30 for seven days or $47 for a year, unless a charter or pier license covers them. This is general information about how the rules work, not legal advice, so check your own situation with FWC before you cast.

The Path From Here to July

The City's timeline shows how quickly the work has moved since the groundbreaking:

  1. January 5–6, 2026: Public groundbreaking ceremony, then construction begins.
  2. April 13, 2026: Demolition of the old pier is complete.
  3. June 17, 2026: Work starts on a trestle along the south side, so construction can continue when weather sends the offshore barges to shelter.
  4. June 26, 2026: First concrete pour for the bents.
  5. September 18, 2026: Mid-Pavilion pour pushes the project past 50 percent of its concrete.
  6. October 7, 2026: Last of 193 pilings driven.
  7. Early 2027: Structural work expected to finish, followed by ipe decking.
  8. July 2027: Scheduled reopening.

The City credits a calm summer for keeping construction on pace. Electrical work, bathroom and storage renovations, and foundation improvements are all underway. With the pilings finished six days ago, the main question left is whether the concrete and decking hold to that schedule through the winter. That puts the reopening about nine months out.

If you own a home near 12th Avenue South, the rebuild's schedule, parking and access may affect your plans for the coming year, especially if you have a sale, a seasonal rental or a purchase coming up before the pier reopens. Maxim Properties follows these Naples projects closely and can help you match your timing to what's happening at the end of the street. Schedule a Consultation when you're ready to talk it through.